Update Cost Plus Adjustment (Price Setting)

This article describes how to update the adjustment for the out-of-the-box Cost Plus strategy.

  1. Navigate to the Company Parameters page, and search for tables with name ending with “CostPlus”. They hold the CostPlus factors.

    Example of tables with factors for Cost Plus strategy, including the fallback “CostPlus” table and tables for specific Pricing Levels.

     

  2. Select a table to modify. Decide for which Pricing Level you want to set up the adjustments. You can either set it for:

    • very specific Pricing Level (for example in “GermanyCostPlus),

    • or for some of the parent Pricing Levels (for example in “GlobalCostPlus),

    • or eventually for all in the table “CostPlus” (called also fallback).

      Note: When the system looks for the actual value of the adjustment, it will start from the table specific for the price list/grid Pricing Level (dependency name) and if not found there, it will traverse up the Pricing Levels via their parents, and if not found, it will try to get it from the CostPlus table.

  3. Define the Plus adjustment (either % or a particular money value, depending on what is used for your business) for a combination of Product Segmentations. If you are curious how your Cost+ is set up, you can review the article .

    Example of “Plus” adjustment for “Global” Pricing Level and specific Product Segments.

     

  4. Recalculate the price list/grid and ensure your adjustment changes are used.