Introduction

The purpose of the project initiation sprint is to set up the project on both the Pricefx side, but also (and more importantly!) on the customer’s side.

...

The duration is typically 2-6 weeks.

Main activities

Typically the project starts when the PMs on both sides start their alignment. For guiding this we have the PFX Implementation Process Overview slide deck. This can be used as a template for the discussion with the customer.

...

  • Setup the proper project governance (Project Board, SteerCo, Architecture board - as needed)

    • Appoint Project team according the agreed roles and manage their allocation

    • In case this is not properly done yet, make a write-up of the business requirements in user stories

    • Follow Pricefx Business User training

    • Plan all activities around needed changes to non-Pricefx systems

    • Plan all change management activities

    • Plan all data readiness related activities – ideally already start this before the actual project start
      Especially data is very important and mostly underestimated. Emphasize this over and over again to our customers!

  • SoW Review & update project timeline

    • Review the SoW together, so there is a common understand on what is agreed contractually. This seems obvious, but very often this very often enlightens the customer on what was agreed we do

    • The project timeline is often created months before the actual start (as negotiations and getting an actual signature can take long). Therefore the plan needs to be updated based on constraints on both sides.

  • Prepare kickoff meeting

    • The kickoff meeting is not the Pricefx kickoff meeting. It is the joint project team’s kickoff meeting. Typically the structure is:

      • The Customer explains about the goals of the project, what they try to achieve etc

      • Our AE explains what Pricefx is

      • The customer’s PM explains the project plan

      • The Pricefx PM explains how we work together

Additional actions

Also in this phase it would be good to plan all meeting cadences already, so everyone’s agenda is blocked. This can be the following meetings:

...