Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

The article provides a detailed overview of the User Acceptance Testing (UAT) phase in a software development project, including prerequisites, tasks before UAT, tasks during UAT, and completion of the project. It also includes examples of project timelines and resource allocations for different project sizes.

Table of Contents
minLevel1
maxLevel6
outlinefalse
stylenone
typelist
printablefalse

For more complex projects, a 2-week UAT period may not suffice. Here's an example of what an extended UAT might entail and the necessary components. It's important to note that planning for a 6-week UAT should be done at the project's outset, and it serves as an illustration for larger projects. The fundamental expectations remain unchanged - the customer retains overall responsibility for UAT, although a QA analyst can provide assistance if needed.

...

Pre-UAT

Pre-UAT

UAT

UAT

# of sprints

Training and prep

SIT

E2E testing

Bug fixing & testing

Total UAT weeks

3

1

1

1

1

2

4

1

1

2

1

5

4 or 5

1

1

2

2

4

6

1

1

3

2

7

6 or 7

1

1

3

3

6

Role

Allocation

PM

same as FS allocation

SA

50 % of FS allocation

CE

50-75 % of FS allocation

IE

25% of FS allocation

QA

50-75 % of FS allocation

...