Table of Contents | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
...
Pre-UAT | Pre-UAT | UAT | UAT | ||
# of sprints | Training and prep | SIT | E2E testing | Bug fixing & testing | Total UAT weeks |
3 | 1 | 1 | 1 | 1 | 2 |
4 | 1 | 1 | 2 | 1 | 5 |
4 or 5 | 1 | 1 | 2 | 2 | 4 |
6 | 1 | 1 | 3 | 2 | 7 |
6 or 7 | 1 | 1 | 3 | 3 | 6 |
Role | Allocation | ||||
PM | same as FS allocation | ||||
SA | 50 % of FS allocation | ||||
CE | 50-75 % of FS allocation | ||||
IE | 25% of FS allocation | ||||
QA | 50-75 % of FS allocation |
...