Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

As for more complex projects 2 weeks of UAT is not enough, here is an example of how longer UAT can look like and what it should contain. Note that 6 weeks of UAT must be planned at the beginning of the project. Customer should be still responsible for UAT, but QA analyst can help if it is required. Note that customer must understand that they must be still prepared for UAT before those 6 weeks, when customer try to do preparation in those 6 weeks, they will not have enough time.

...

Proposed timelines and allocations:

Pre-UAT

Pre-UAT

UAT

UAT

# of sprints

Training and prep

SIT

E2E testing

Bug fixing & testing

Total UAT weeks

3

1

1

1

1

2

4

1

1

2

1

5

4 or 5

1

1

2

2

4

6

1

1

3

2

7

6 or 7

1

1

3

3

6

Role

Allocation

PM

same as FS allocation

SA

50 % of FS allocation

CE

50-75 % of FS allocation

IE

25% of FS allocation

QA

50-75 % of FS allocation

Internal description as Packages:

...

In case customer will not choose the size of UAT package, it will be selected based on number of Feature Sprints

Ppt slide deck which can be shared with the customer:

...

.

...

...

Info

You can learn about UAT on the project here.

...